Reported work packages: 32
08/09/2024
-
updated on 08/09/2024 12:40 PM
- Project status changed from On track to Off track
04/27/2024
-
Feature #73: [FEAT]: Add Typst Icon (Project: presence.nvim)updated on 04/27/2024 07:33 PM
- Status changed from New to Specified
-
Feature #73: [FEAT]: Add Typst Icon (Project: presence.nvim)created on 04/27/2024 07:28 PM
04/18/2024
-
updated on 04/18/2024 04:53 PM
- Status changed from New to Closed
-
created on 04/18/2024 03:21 PM
04/17/2024
-
Phase #46: v1.0 (Project: presence.nvim)updated on 04/17/2024 09:49 PM
- Dates changed by changes to related Task #42: Setup versioning
- Duration changed from 272 days to 380 days
-
Phase #46: v1.0 (Project: presence.nvim)updated on 04/17/2024 09:49 PM
-
Comment added
Updated automatically by changing values within child work package #42
- Working days set to include non-working days
-
Comment added
-
Task #42: Setup versioning (Project: presence.nvim)updated on 04/17/2024 09:49 PM
- Finish date changed from 12/22/2023 to 08/31/2024
- Total work set to 1h
- Duration changed from 5 days to 258 days
- Working days set to include non-working days
- Total remaining work set to 1h
-
updated on 04/17/2024 09:49 PM
- Finish date changed from 12/05/2023 to 04/30/2024
- Start date changed from 12/05/2023 to 04/30/2024
- Total work set to 0.5h
- Total remaining work set to 0.5h
-
Phase #45: Project rewrite (Project: presence.nvim)updated on 04/17/2024 09:49 PM
- Dates changed by changes to related Task #58: Go over the whole file
- Finish date changed from 05/31/2024 to 07/12/2024
- Duration changed from 115 days to 145 days
-
Task #57: Document init.lua (Project: presence.nvim)updated on 04/17/2024 09:49 PM
- Dates changed by changes to related Task #58: Go over the whole file
- Finish date changed from 05/31/2024 to 07/12/2024
- Duration changed from 115 days to 145 days
04/03/2024
-
updated on 04/03/2024 03:28 PM
- Project status changed from Off track to On track
-
Damn you time! (Project: presence.nvim)created on 04/03/2024 03:24 PM
01/09/2024
-
updated on 01/09/2024 03:40 PM
- Project status changed from On track to Off track
12/05/2023
-
General: Welcome to Presence.nvim! (Project: presence.nvim)updated on 12/05/2023 07:05 PMSubject: Welcome to Presence.nvim!
Hey everyone,
I'm Jiří Štefka, the person steering the ship for Presence.nvim. 👋 I pi... -
Support: Rules (Project: presence.nvim)created on 12/05/2023 07:01 PMWhile the same rules as in General apply, here are some additional guidelines specific to the support forum:
Ask Questi... -
created on 12/05/2023 06:45 PMIf you're unsure where to ask in need of assistance, you're in the right place! Feel free to post your questions and see...
-
General: Rules (Project: presence.nvim)created on 12/05/2023 06:38 PMWhile no one likes it it still has to be done. So here are some ground rules:
Respect Each Other:
Treat fellow forum ... -
General: Welcome to Presence.nvim! (Project: presence.nvim)created on 12/05/2023 06:21 PMSubject: Welcome to Presence.nvim!
Hey everyone,
I'm Jiří Štefka, the person steering the ship for Presence.nvim. 👋
I pi... -
Here comes the work (Project: presence.nvim)created on 12/05/2023 02:52 PM
-
updated on 12/05/2023 11:51 AM
- Project status description set (Details)
-
Welcome (Project: presence.nvim)created on 12/05/2023 12:12 AM
12/04/2023
-
created on 12/04/2023 09:39 PM